Residential Contractors

(843) 846 - 2500

Gitlitz Garage: July 2007



July 3, 2007 -- The exterior trim is getting primed and ready for trim paint.


July 11, 2007 -- Today, electrical rough in will be started (and finished). These boxes (near the center) are for the garage door opener.


July 12, 2007 -- The electrical rough in is complete. Mechanical inspection is next.


July 12, 2007 -- A brick sidewalk will be built between the cottage and garage.


July 12, 2007 -- A brick sidewalk will be built between the cottage and garage.


July 18, 2007 -- The garage is being painted. The trim is green like the house and the garage is dark gray. The light places have not been painted yet. The primer is light gray.


July 21, 2007 -- The bottom of the deck and roof have been sprayed with open cell insulation. The walls will be insulated in the next day or two.


July 23, 2007 -- The outside of the garage has a full coat of final paint and trim.


July 24, 2007 -- The deck above the storage room is getting a waterproof coating. Once it is finished, a deck will be built.


July 24, 2007 -- The deck waterproofing fabric can be seen from the cottage steps. The posts for deck railings can also be seen.


July 26, 2007 -- The deck waterproofing should be completed today. After that a wooden deck and handrails will be built.